Tesla has opened a Supercharger that automatically adjusts its power use to local grid limits. The approach lets charging stations open without waiting for grid upgrades.
How the Cloverdale station works
Tesla opened the station in Cloverdale, California, on November 16. It uses utility PG&E’s Flex Connect service, which lets customers with adjustable electricity needs connect without waiting for grid capacity upgrades.
Cloverdale is the first publicly identified Tesla station using direct grid communication through the IEEE 2030.5 standard. When strain affects the local grid, PG&E can temporarily curb the station’s electricity use by sending limits straight to its V4 Supercharger power cabinets.
Get the latest EV news first. Follow us on:
PG&E sends hourly power limits a day in advance, and the chargers adjust automatically. This gives the station a schedule of available power instead of one fixed limit throughout the day.
Open seven days a week for 24 hours a day, the station provides eight charging stalls with power of up to 500 kW each. It is at Penny Faire Plaza, 421 S Cloverdale Boulevard. Non-Tesla EVs can charge there with a NACS adapter.
More power without waiting for upgrades
Tesla requested 2 megawatts of electrical capacity for its Supercharger sites. Flex Connect gave Tesla access to that full amount immediately and nearly all the time, while allowing PG&E to set lower limits during periods of high demand.
During peak periods, such as hot summer evenings, a site can be restricted to 0.5 megawatts under the arrangement. Without Flex Connect, a Supercharger site seeking the higher capacity could instead be limited to that lower level year-round.
The service uses PG&E’s cloud-based system for managing distributed energy resources, developed and deployed with Microsoft and Schneider Electric. The system produces the advance hourly power-limit forecast used to manage participating customers’ electricity consumption.
PG&E announced its Flexible Service Connection offering on April 28, 2025. To qualify, a location must be within its service area, be able to adjust energy consumption and need grid reinforcement work that would take more than 12 months.
More Superchargers in development
To power new Supercharger stations along major highway travel corridors, Tesla applied to PG&E for electricity service in early 2024. PG&E said the grid upgrades needed for Tesla’s sites would otherwise take a few years.
Flex Connect also helped Tesla increase capacity at two new California Supercharger sites, Santa Nella and Upper Lake. Across the programme, PG&E had expedited connections for four sites, with several more participating locations in development.
Numerous additional Tesla Supercharger sites are being developed with Flex Connect. Tesla estimated that a typical project in PG&E’s service area could open more than two years earlier using the arrangement.
More stations like Cloverdale are expected to open across PG&E’s service area. Opening stations before grid upgrades are finished is intended to help Tesla expand its charging network faster.
Why it matters
For EV drivers, this approach offers a way to open charging locations while longer grid upgrades continue. The trade-off is variable station power when the grid is busy, rather than a permanent restriction while upgrades are pending.
Key Specs
- Maximum power per stall: Up to 500 kW
- Access hours: 24 hours a day, seven days a week
- Site limit during peak periods under Flex Connect: 0.5 megawatts
✎ Images and news sourced from: pgecorp.com, teslanorth.com, notateslaapp.com, driveteslacanada.ca, frandroid.com, canarymedia.com, evengineeringonline.com, tesla.com.